Project Installed Capacity in MW Status

Kirthai-I

390

DPR under appraisal by CEA.

Kirthai-II

930

DPR approved by CEA. To be implemented by JKSPDC under EPC.

Ujh (Multipurpose Project)

178

To be implemented jointly by Dept of Irrigation and Flood Control, GoJK and JKSPDC. EIA/EMP studies underway.

Sawalkote

1856

TEC has been cleared by CEA. Development of project under consideration by GoJK.

Lower Kalnai

48

SAC approved termination of EPC/PMC contracts. To be retendered.

Parnai

37.5

Project under implementation through EPC contract awarded to M/s Patel Engineering. 35% progress achieved. Expected date of completion is in 2021.

New Ganderbal (NGHEP)

93

Updation of DPR under way and revalidation from CEA to be done. To be retendered after revalidation.

Ratle

850

Being Developed in joint venture with NHPC. PIB in progress. To be tendered soon.

Dah & Hanu

18

Dah commissioned. Hanu to be commissioned in Oct 2019.

Trisha-Thoise

24

DPR accorded TEC. Project proposed to be developed as a multipurpose project. The project shall be tendered after approval to sanction of 100% funds by GoI.

Ratan Nag

18

DPR prepared departmentally. TEC pending. The project shall be tendered after approval to sanction of 100% funds by GoI.

Bonar Lolab

24

DPR prepared departmentally. TEC pending. The project shall be tendered after approval to sanction of 100% funds by GoI.

PMDP (Prime Minister's Development Program) Projects - Phase I

Karnah

12

Letter of Award issued for EPC and PMC Contracts

Matchil Kalaroos - I

25

DPR prepared departmentally. EPC contract to be retendered

Durbuk-Shyok

19

DPR accorded TEC. EPC tenders under evaluation

Phagla

14.1

DPR accorded TEC. EPC work retendered.

Tamasha

12

DPR accorded TEC. EPC contract retendered.

Ans-II

23

DPR accorded TEC. EPC contract retendered.

Mangdum-Sangra

19

DPR accorded TEC. EPC contract retendered.

Sankoo

18

DPR accorded TEC. EPC contract retendered.

Mohra

12

DPR prepared departmentally. TEC pending.

Dessa

16.5

DPR prepared departmentally. TEC pending.

PMDP (Prime Minister's Development Program) Projects - Phase II

Iqo-Upshi

25

DPR accorded TEC. To be tendered.

Upshi

15

DPR prepared departmentally. TEC pending.

Nimu-Chilling

25

DPR accorded TEC. To be tendered.

Drass Stage-I

24

DPR accorded TEC. To be tendered.

Kargil-Hunderman

24

DPR accorded TEC. To be tendered.

Kulan-Ramwari

21

DPR accorded TEC. To be tendered.

Kalaroos-II

21

DPR accorded TEC. To be tendered.

8 hydro power projects, between 2MW and 10MW capacities, handed over to JKSPDC by JaKeDA to be implemented by JKSPDC. DPRs of these projects are handed over. Apart from this, 5 more project with PFRs also handed over to JKSPDC for development.